WillScot details modular delivery of NFL training facility in 2 1/2 months

WillScot detailed delivery of the Los Angeles Rams' 64,670 sq ft temporary facility built in 2024. Assembling 88 modular units took a 2 1/2-month onsite phase after nearly a year of planning and 75% offsite work.

AI 生成概念示意圖,非實際產品或事件照片。
AI-generated concept illustration; not an event photograph.

WillScot senior director Sven Louis outlined the delivery of the Los Angeles Rams' temporary training complex in Woodland Hills, California. Designed by Gensler, the 64,670-square-foot complex comprises 88 modular units across four buildings. While onsite delivery and installation took 2 1/2 months, planning began in February 2023, and about 75% of construction was done off site starting in February 2024.

Key takeaways

  • Prefabricating roughly 75% of the build off site enabled civil work and building repurposing to proceed in parallel before crane placement on the foundation.
  • Special structural engineering included laying steel sheets across the weight room floor to absorb dropped weights and reinforcement for industrial laundry units.

Source:Construction Dive Read the original ↗