Decommissioning works at the former Dungeness A nuclear site include dismantling eight 800-tonne boilers. Contractor Aureos is deploying a specialized jack-and-slide setup to handle these heavy components following preparatory operations.
Decommissioning operations at the former Dungeness A nuclear station in Kent have reached a major milestone involving the clearance of eight massive boiler units, each with a mass of 800 tonnes. Nuclear Restoration Services engaged contractor Aureos to execute the dismantling. Following four years of enabling preparations, teams are using a specialized jack-and-slide mechanism to shift the components. This phase will eliminate approximately one-third of the above-ground installations on the 20-hectare coastal parcel.
Key takeaways
- Crews are employing a specialized jack-and-slide rig to transport and extract eight 800-tonne boilers.
- Nuclear Restoration Services tasked contractor Aureos with carrying out the site clean-up project.
- The scope clears roughly one-third of above-ground facilities across the 20-hectare site after four years of enabling works.